Parking Garage Construction Update - May 17, 2018

Project Status & Two Week Look Ahead

Earthwork for Perimeter Supports and Shoring, as well as Excavations for lagging, have been completed as of 5/11/2018. Aggregeate Pier and Survey work has been completed (5/9/2018). The City's Seismic monitoring and testing consultant has been on-site throughout vibratory operations to ensure state regulatory confines are adhered to with regard to abutting properties.

Streetwork and Facility Excavations and preparation for structural footings are underway, and are projected to be completed by the end of July, 2018.

Removal of Site Material and associated Trucking will continue at the site throughout the month of May and into June.

The City's Impact Advisory Group (AIG) meeting previously scheduled and posted will be held in the 1st floor conference room at City Hall at 6:30PM on 5/17/2018.