Night Work Scheduled for Mass DOT’s Route 1 Project
There will be some nighttime milling operations next week on the current Route 1 project. Most of it will be in sections with lane shift. North and South bound are separated by guardrail and will be handled by Northbound first and then Southbound. Milling should take about 6 nights, starting on/around Sunday, 5/5 and ending on/around Monday, 5/13. The schedule is not locked in stone as milling is weather dependent and could change if an issue comes up. Below are the details:
Night 1 Northbound - MBTA Bridge to just north of Pomodori
Night 2 Northbound - just North of Pomodori to Pond St
Night 3 Northbound - Pond St to Merrimac St
Night 4 Southbound - Merrimac St to Pond St
Night 5 Southbound - Pond St to Rotary
Night 6 Southbound - Rotary to the MBTA Bridge
If you have any questions or complaints, please reach out to Carmen C. Ilardi, Resident Engineer @ the Massachusetts Department of Transportation. He can be reached at 617-866.8760 or via email atCarmen.Ilardi@dot.state.ma.us