  • Milling operations on the western end of the project (where 180 Storey Ave. is ) are complete. The Contractor is milling nightly at the east end, which is on the other side of Rte. 95, and should be complete by the end of this week.
  • The schedule for the milling of the bridge deck over Rte. 95 is still pending.
  • The next major operations will be the placement of drainage structures and traffic loops. We will reach out to the Contractor to request that this work be performed during the daytime.